Grantham Highway improvements

A series of major highway works are scheduled to take place in Grantham throughout 2024.

Below is a list of the planned works:

Spring 2024

  • SKDC’s proposed changes to the Market Place in the town centre
  • Reconstruction of sections of High Street, Great Gonerby and Gonerby Road, Grantham
  • Construction of a new pedestrian crossing at High Street, Great Gonerby

Summer 2024

  • Reconstruction of Dysart Road
  • Reconstruction of Alma Park Road
  • Construction of a new Greenhill Road / Barrowby Road pedestrian crossing
  • Construction of a new Barrowby Road / Poplar Farm pedestrian crossing
  • SKDC’s proposed changes to Station Road and A52/A607 junction

Aims and benefits

  • improved road surfacing resulting in safer and smoother journeys for residents
  • improved crossing facilities for pedestrians, cyclists and others not traveling by car
  • improved quality of life for residents of Grantham

Cost and funding

The total cost for the roadworks (excluding SKDC’s Market Place and Station Approach works) will cost nearly £4 million and is being funded by us.

Timeline

*All future dates are projected and subject to change dependent on external factors.

Weekly works progress

A series of major highway works are taking place in Grantham until December 2024.

Here is what’s happening during w/c 2 September.

Market Place

Activity Dates
Paving (2 gangs) on Conduit Lane Monday 2 - Friday 6 September
Continued engagement and dialogue with businesses/residents and local councillors Monday 2 - Friday 6 September
Extra work from SKDC – jetwashing existing paving, removing vegetation Monday 2 - Friday 6 September

Station Approach

Activity Dates
Continued engagement and dialogue with businesses/residents and local councillors Monday 2 - Friday 6 September
Install Nall sockets Tuesday 3 - Wednesday 4 September
Trim subbase Thursday 5 September
Remove, replace and reset and paint iron works as per schedule Friday 6 - Tuesday 10 September

Dysart Road

Activity Dates
Footway works, drainage works, kerbing and channel replacements continues along the south side of Dysart Road from Trent Road to the Co-op Monday 2 - Friday 6 September
Drainage works continue from Ventor Avenue towards Dysart Way Monday 2 - Friday 6 September
Footway surfacing ongoing from Dysart Rail bridge heading towards Kempton Way Monday 2 - Friday 6 September
Footway surfacing from Barrowby Gate to the Avenue Monday 2 - Friday 6 September
Pedestrian Tactile Crossing installation / replacements Monday 2 - Friday 6 September