Grantham Highway improvements

Weekly works progress

A series of major highway works are taking place in Grantham until December 2024.

Here is what’s happening during w/c 18 November.

Station Approach

Activity 

Dates

Continued engagement and dialog with businesses/residents and local councillors.

Monday 18 November – Friday 22 November

Phase 4 – Sankt Augustin Way

Activity

Dates

Installation of kerbs and edgings.

Monday 18 November - Wednesday 20 November

Install traffic signal NAL sockets.

Monday 18 November - Tuesday 19 November

Trim sub-base.

Thursday 21 November

Remove and replace iron works.

Thursday 21 November – Friday 22 November

Install traffic signal poles and heads to Phases 2 and 3.

Monday 18 November – Thursday 21 November

Dysart Road

Activity

Dates

Employ temporary traffic lights along Dysart Road at Trent Road and Barrowby Gate in parallel with the one-way closure, to provide safe working space for deeper drainage works. These will move away from Trent Road after the works on Wednesday 13 November once surfacing is completed.

Monday 18 November – Friday 22 November

Continue drainage works on north side of Dysart Road, from Yarmouth Avenue to Valley Road..

Monday 18 November – Friday 22 November

No night-time road closures on Dysart Road will be required.

Monday 18 November – Friday 22 November

TM north side of Dysart for daytime works – closure will remain as westbound.

Monday 18 November – Friday 22 November

Northside footway works, including tactile crossings from Yarmouth Avenue to Trent Road.

Monday 18 November – Friday 22 November

Footpath surfacing works from Yarmouth Avenue to Barrowby Gate and from Barrowby Gate to Valley Road.

Monday 18 November – Friday 22 November