Weekly works progress
A series of major highway works are taking place in Grantham until December 2024.
Here is what’s happening during w/c 18 November.
Station Approach
Activity |
Dates |
---|---|
Continued engagement and dialog with businesses/residents and local councillors. |
Monday 18 November – Friday 22 November |
Phase 4 – Sankt Augustin Way
Activity |
Dates |
---|---|
Installation of kerbs and edgings. |
Monday 18 November - Wednesday 20 November |
Install traffic signal NAL sockets. |
Monday 18 November - Tuesday 19 November |
Trim sub-base. |
Thursday 21 November |
Remove and replace iron works. |
Thursday 21 November – Friday 22 November |
Install traffic signal poles and heads to Phases 2 and 3. |
Monday 18 November – Thursday 21 November |
Dysart Road
Activity |
Dates |
---|---|
Employ temporary traffic lights along Dysart Road at Trent Road and Barrowby Gate in parallel with the one-way closure, to provide safe working space for deeper drainage works. These will move away from Trent Road after the works on Wednesday 13 November once surfacing is completed. |
Monday 18 November – Friday 22 November |
Continue drainage works on north side of Dysart Road, from Yarmouth Avenue to Valley Road.. |
Monday 18 November – Friday 22 November |
No night-time road closures on Dysart Road will be required. |
Monday 18 November – Friday 22 November |
TM north side of Dysart for daytime works – closure will remain as westbound. |
Monday 18 November – Friday 22 November |
Northside footway works, including tactile crossings from Yarmouth Avenue to Trent Road. |
Monday 18 November – Friday 22 November |
Footpath surfacing works from Yarmouth Avenue to Barrowby Gate and from Barrowby Gate to Valley Road. |
Monday 18 November – Friday 22 November |