Grantham Highway improvements

Weekly works progress

A series of major highway works are taking place in Grantham until December 2024.

Here is what’s happening during w/c 2 September.

Market Place

Activity Dates
Paving (2 gangs) on Conduit Lane Monday 2 - Friday 6 September
Continued engagement and dialogue with businesses/residents and local councillors Monday 2 - Friday 6 September
Extra work from SKDC – jetwashing existing paving, removing vegetation Monday 2 - Friday 6 September

Station Approach

Activity Dates
Continued engagement and dialogue with businesses/residents and local councillors Monday 2 - Friday 6 September
Install Nall sockets Tuesday 3 - Wednesday 4 September
Trim subbase Thursday 5 September
Remove, replace and reset and paint iron works as per schedule Friday 6 - Tuesday 10 September

Dysart Road

Activity Dates
Footway works, drainage works, kerbing and channel replacements continues along the south side of Dysart Road from Trent Road to the Co-op Monday 2 - Friday 6 September
Drainage works continue from Ventor Avenue towards Dysart Way Monday 2 - Friday 6 September
Footway surfacing ongoing from Dysart Rail bridge heading towards Kempton Way Monday 2 - Friday 6 September
Footway surfacing from Barrowby Gate to the Avenue Monday 2 - Friday 6 September
Pedestrian Tactile Crossing installation / replacements Monday 2 - Friday 6 September