The Dysart Road improvement project will see the following works carried out in Grantham:
- rebuilding the whole of Dysart Road, including footways, from its junction with Sankt Augustin Way to the A1 overbridge
- replacing old drainage and kerbs
- amending the dropped kerb arrangements along the road
Aims and benefits
- smoother journeys for those travelling by car
- improved footways for those traveling on foot
- upgraded highways drainage for the area
Cost and funding
The estimated cost is £3 million, with the scheme being fully funded by us.
Timeline
- March 2024: Public information event about this and other Grantham roadworks held
- July 2024: Contractor appointed
- July 2024: Main construction starts
- December 2024*: Project completion
*All future dates are projected and subject to change dependent on external factors.