Somerby Hill roundabout works progressing well.
What we achieved in February
Phase Two
- Undertook inspections across site
Phase Three
- West side of site – began main piling works / continued western abutment works including concrete and shuttering / completed access track filling from B1174 roundabout to Pond B
- East side of site – completed ground investigations near east embankment / continued rock processing and main road excavation / continued second phase of Somerby Hill roundabout works including drainage, ducting, kerbing and surfacing
What's happening in March
Phase Three
- West side of site – carry out pile excavation works and cropping / off-site trial erection of bridge pier / reinforcement to the pier 1 bridge bases
- East side of site – lay additional surfacing at Somerby Hill roundabout / continue rock processing and main road excavation / construct access track and soakaways between Somerby Hill and Whalebone Lane
Current/ongoing traffic restrictions and closures
- Ongoing lane closures on the B1174 roundabout until the end of the scheme
- Temporary traffic signals and lane closures as needed at Somerby Hill Roundabout until Spring 2022
Upcoming traffic restrictions and closures
- N/A