Grantham Southern Relief Road March update

GSRR - March update

Somerby Hill roundabout works progressing well.

What we achieved in February

Phase Two

  • Undertook inspections across site

Phase Three

  • West side of site – began main piling works / continued western abutment works including concrete and shuttering / completed access track filling from B1174 roundabout to Pond B
  • East side of site – completed ground investigations near east embankment / continued rock processing and main road excavation / continued second phase of Somerby Hill roundabout works including drainage, ducting, kerbing and surfacing

What's happening in March

Phase Three

  • West side of site – carry out pile excavation works and cropping / off-site trial erection of bridge pier / reinforcement to the pier 1 bridge bases
  • East side of site – lay additional surfacing at Somerby Hill roundabout / continue rock processing and main road excavation / construct access track and soakaways between Somerby Hill and Whalebone Lane

Current/ongoing traffic restrictions and closures

  • Ongoing lane closures on the B1174 roundabout until the end of the scheme
  • Temporary traffic signals and lane closures as needed at Somerby Hill Roundabout until Spring 2022

Upcoming traffic restrictions and closures

  • N/A

Published: 3rd March 2022