Road re-opens for up to four weeks under temporary traffic signals.
What we achieved in February
Roman Bank – Phases 5 and 6
- Re-opened Roman Bank under temporary traffic signals
- Excavated 5 trial holes to determine drainage viability
- Raised dropped kerbs across 4 accesses to prevent water discharge from road onto private property
- Laid 120m of new channels and 120m of new footpath edgings
- Excavated 120 tonnes of old footpath
- Laid 180 tonnes of footpath building materials
What's happening in March
Roman Bank – Phases 5 and 6
- Begin laying new road surfacing during the second half of the month
Current/ongoing traffic restrictions and closures
- Full road closure between the Muirfield Drive and North Shore Road junctions on Roman Bank
- Diversion via the A52 / C541 / A158 at the Gunby dual carriageway, and vice versa
Upcoming traffic restrictions and closures
- N/A