Road users can now drive on the second of four Lincoln Eastern Bypass roundabouts.
What we achieved in October
- Completed essential works at Sleaford Road roundabout and opened up to road users
- Steel beams for River Witham Viaduct lifted, placed and braced.
- Continue construction of wing walls for Lincoln Road underpass
- Superstructure delivered and assembled for new Hawthorn Road footbridge
- Completed earthworks and continued concrete works for Heighington Road bridge
- Progressed with construction of bridge bases for Bloxholm Lane footbridge
- Continued kerbing, drainage, street lighting, earthworks and surfacing at Wragby Road roundabout
- Started surfacing between Sleaford Road and Lincoln Road
Continued drainage works between Greetwell Road and Wragby Road; and Branston Brook to Heighington Road - Started drainage, earthworks, street lighting and kerbing for new Greetwell Road roundabout
- Continued sub-base, gullies and kerbings between Sleaford Road and Lincoln Road
- Continued post-excavation archaeological reporting
What’s happening in November
- Complete wing wall construction, waterproof walls and carry out drainage works for Lincoln Road underpass
- Continue construction of River Witham Viaduct, including wing wall construction and decking rebar
- Lift Hawthorn Road footbridge superstructure into place and begin parapet works
- Complete bridge base construction and begin building the abutment walls for the new Bloxholm Lane footbridge
- Continue construction of Heighington Road bridge, including water-proofing and edge beam works
- Complete kerbing, drainage, street lighting, earthworks and surfacing at Wragby Road roundabout
- Continue drainage works between Greetwell Road and Wragby Road; Washingborough Road and Greetwell Road; and Branston Brook and Heighington Road.
- Complete essential works at Greetwell Road roundabout and opened up to road users
- Complete surfacing between Sleaford Road and Lincoln Road
- Continue post-excavation archaeological reporting
Upcoming traffic restrictions and closures
- Night-time 3-way traffic signals at Wragby Road roundabout from 11 to 22 November, 6:30pm to 6am
Current/ongoing traffic restrictions and closures
- Full night-time closure at Wragby Road roundabout until 8 November, 6:30pm to 6am
- Full 24/7 closure of Greetwell Road from 14 October to 29 November
- Temporary speed restrictions on Washingborough Road, Greetwell Road, Lincoln Road, Sleaford Road and Hawthorn Road
- Weekday off-peak two-way traffic signals (9:30am - 3:30pm) until mid-December on A15 Sleaford Road
- Temporary traffic signals on Hawthorn Road, Greetwell Road, Washingborough Road and Lincoln Road to allow safe access for construction vehicles and machinery
- Temporary 200m path diversion on the Sustrans route along the River Witham
- Full closure of Heighington Road, Bloxholm Lane and Greetwell Fields Lane