Improvements successfully re-commence.
What we achieved in October
Roman Bank – Phases 4B and 5
- Planed off 650 tonnes of asphalt within Phase 5
- Excavated 140m of new gas trench to facilitate Cadent's new main and connections
- Broke out and disposed of 250m of old kerbs
- Removed 280 linear meters of old footpath asphalt and replaced with new
- Installed 8 new gully pots to improve drainage on Roman Bank
Hoylake Drive
- Planed off and disposed of 450 tonnes of old carriageway
- Excavated and disposed of 1200 tonnes of old concrete and muck
- Reinstated 1200 tonnes of new capping/Type 1
- Laid 600 tonnes of new asphalt
What's happening in November
Roman Bank – Phases 4B and 5
- Install final 90m of new SW drainage and 3 new manholes.
- Replace kerbs
- Work with utility companies to lower various service crossings to safe depths
Current/ongoing traffic restrictions and closures
- Full road closure between the Muirfield Drive and Brancaster Drive junctions on Roman Bank
- Diversion via the A52 / C541 / A158 at the Gunby dual carriageway, and vice versa
Please note that pedestrian access will be maintained for residents and businesses, except when works are being carried directly outside a property (exact location will change as the scheme progresses).
Those affected will be notified in advance and are encouraged to speak to the site team to discuss any accommodations that can be made.
Private and on-street parking within the immediate area of works will also be restricted.
However, restrictions on two 'limited-time' parking zones on Sea View Road, between the junction with Hoylake Drive and the junction with Roman Bank, will be suspended during the project to provide alternative parking.