Improvement works are nearing completion.
What happened in October
- Started footway construction and installation of traffic signal equipment, safety barriers, and new road signs
- Completed kerbing to northbound B1518
- Completed final surfacing and carriageway markings of the roundabout
- Completed installation of new drainage and street light columns
- Completed installation of carriageway traffic signal loops
What's happening in November
- Erect traffic monitoring cameras
- Complete surfacing to the B1518 Sleaford
- Continue construction of footways and a maintenance track to central island
- Continue site fencing and installation of safety barriers and new road signs
- Continue installation of traffic signal equipment
- Carry out tree-planting and grass-seeding
Current/ongoing traffic restrictions and closures
- Temporary 30mph speed restriction and 50mph speed restriction on the A17 dual carriageway
- Reduced lanes on approaches to roundabout
- Signalised pedestrian crossing to central roundabout for workforce use
- Pedestrian diversion via the A17 overbridge