May will see work begin on drainage and kerbing works to the roundabout and continued progress on ditch and A15 reconstruction between Navenby and Brauncewell.
What we achieved in April
- Progress with Anglian Water diversion
- Diversions planned on A15 North with BT and asset protection works with WPD
- Continued earthworks on the central island, including filling with sub-base materials
- Prepared the A17 dual carriageway ditch for carriageway widening and drainage works
- Continued carriageway widening to the B1518 Lincoln Road Sleaford, including kerbing and drainage works
- Began carriageway reconstruction works on the A15, between Navenby and Brauncewell
What's happening in May
- Continue Anglian Water diversion
- Begin drainage and kerbing works to the roundabout's central island
- Continue works to the ditch on the A17 dual carriageway ahead of drainage installation.
- Continue carriageway widening to the B1518 Lincoln Road Sleaford, including surfacing
- Continue carriageway reconstruction works on the A15, between Navenby and Brauncewell
Current/ongoing traffic restrictions and closures
- Temporary 30mph speed restriction and 50mph speed restriction on the A17 dual carriageway
- Narrowed lanes on the A17 dual carriageway on the approach to the roundabout
- Reduced lanes on approach to roundabout during off-peak times
- Signalised pedestrian crossing facility on A17, and to central roundabout for workforce
- Rolling road closures on the A15, between Navenby and Brauncewell
Upcoming traffic restrictions and closures
- N/A