The project is well underway with utility diversions and the early stages of construction progressing.
What we achieved in March
- Completed Phase 1 and started Phase 2 of Anglian Water diversions
- Removed all five splitter islands
- Erected six temporary streetlight columns in lieu of the splitter island streetlight columns
- Installed five road crossings on the A17 & A15
- Constructed a safe loading/unloading area in the central island
- Commenced earthworks on the central island with deep excavation and sub-base construction
- Piped and backfilled the drainage ditch on the A15 North
What's happening in April
- Continue Phase 2 Anglian Water diversion
- Divert Western Power HV cable on the A15 North
- Divert BT assets on the A15 North
- Continue earthworks on the central island and sub-base construction
- Commence drainage works on the central island
- Continue works to the ditch on the A17, ready for carriageway widening
- Carry out carriageway widening, including kerbing to the B1518 Lincoln Road Sleaford
- Begin carriageway reconstruction works on the A15, between Navenby and Brauncewell
Current/ongoing traffic restrictions and closures
- Temporary 30mph speed restriction and 50mph speed restriction on the A17 dual carriageway
- Narrowed lanes on the A17 dual carriageway on the approach to the roundabout
- Reduced lanes on approach to roundabout during off-peak times
- Signalised pedestrian crossing facility on A17, and to central roundabout for workforce
Upcoming traffic restrictions and closures
- N/A