What we achieved in November working on phases 3 and 4 of the Skegness Roman Bank Highway Improvements.
Phase 3 – from 161 Roman Bank to the Co-op access
- Continued construction of a new pedestrian crossing at the junction of Roman Bank and Seaview Road
- Installed 140m of new drainage pipes
- Installed and connected 15 new gullies
- Removed and replaced 150m of old kerbs and 100m of old footpath
- Placed additional utility crossings under the road to future-proof Roman Bank for service providers
Phase 4 – from the Co-op access to 182 Roman Bank
- Installed 100m of BT ducting to facilitate diversion works
What's happening in December
Phase 3 – from 161 Roman Bank to the Co-op access
- Continue construction of a new pedestrian crossing at the junction of Roman Bank and Seaview Road
Phase 4 – from the Co-op access to 182 Roman Bank
- Continue installing new storm gullies
- Continue removing old footpaths and kerbs and replace with new
- Excavate the road and replace with asphalt to binder level
Current/ongoing traffic restrictions and closures
- Full road closure between the Co-op access to 182 Roman Bank
Upcoming traffic restrictions and closures
- N/A
Please note that pedestrian access will be maintained for residents and businesses, except when works are being carried directly outside a property (exact location will change as the scheme progresses).
Those affected will be notified in advance and are encouraged to speak to the site team to discuss any accommodations that can be made.
Private and on-street parking within the immediate area of works will also be restricted. However, restrictions on two 'limited-time' parking zones on Sea View Road, between the junction with Hoylake
Drive and the junction with Roman Bank, will be suspended during the project to provide alternative