Works across the entire Lincoln Eastern Bypass site continues, ahead of the new road opening later this year.
What we achieved in September
- Continued drainage, street lighting, kerbing, fence installation and road surfacing between Wragby Road to Greetwell Road
- Started weekend road closures at Greetwell Road for final roundabout works, including road markings, signage and street-lining.
- Continue drainage works / begin street-lighting and kerbing works between Greetwell Road to Washingborough Road
- Completed retention pond near new Washingborough Road roundabout
- Began footway edging and surfacing between Washingborough and Lincoln Road (Branston)
- Completed road markings, street-lining, kerbing and surfacing at Lincoln Road roundabout
- Started final road surfacing between Lincoln Road (Branston) and Sleaford Road
- Installed permanent parapets at Hawthorn Road footbridge
- Completed concrete works for Greetwell footbridge
- Completed wing wall stringcourses and deck waterproofing / installed verge ducts, deck kerb and drainage units for River Witham Viaduct
- Completed finishing works / progresses approach paths for South Delph footbridge
- Completed Hawthorn retaining wall
- Installed kerbs, deck/drain units and carried out verge concrete works and deck water-proofing at Market Rasen Line rail bridge deck
- Completed concrete finishing works at Bloxholm Lane footbridge
What's happening in October
- Complete sign installation and street lighting change at Wragby Road
- Complete drainage, street lighting and kerbing / continue fence installation and road surfacing between Wragby Road to Greetwell Road
- Complete road markings, signage and street-lining on Greetwell Road roundabout
- Continue drainage works, surfacing and kerbing works between Greetwell Road to Washingborough Road
- Continue footway edging and surfacing /begin road surfacing, road markings and signage between Washingborough and Lincoln Road (Branston)
- Complete final road surfacing, road markings and signage between Lincoln Road (Branston) and Sleaford Road
- Continue final parapet works at Hawthorn Road footbridge
- Install parapets and construct approach paths for Greetwell footbridge
- Complete parapets, deck joints, concrete works and wing wall stringcourses for River Witham Viaduct
- Complete approach paths for South Delph footbridge
- Fit metal railings for Lincoln Road Underpass
- Carry out works to north wing wall stringcourses / progress parapets for Market Rasen Line rail bridge deck
- Install metal parapets and construct approach paths for Bloxholm Lane footbridge
Upcoming traffic restrictions and closures
- Weekend road closures at Lincoln Road (Branston) from 6am Saturday morning until 6am Monday morning (road may be re-opened before 6am on Monday morning, dependant on how the works progress)
- 3-5 October / 10-12 October
- Weekend road closures at Greetwell Road from 6am Saturday morning until 6am Monday morning (road may be re-opened before 6am on Monday morning, dependant on how the works progress)
- 3-5 October / 10-12 October / 17-19 October / 24-26 October
Current/ongoing traffic restrictions and closures
- Full 24/7 closure of Washingborough Road and Hawthorn Road
- Full 24/7 closure of Bloxholm Lane and Greetwell Fields Lane (new Bloxholm link off of Sleaford Road open)
- Temporary speed restrictions on Heighington Road, Greetwell Road, Lincoln Road and Sleaford Road
- Temporary 200m path diversion on the Sustrans route along the River Witham
*Please note this information is accurate as of the time of publication