Works across the entire Lincoln Eastern Bypass site continues, ahead of the new road opening later this year.

What we achieved in September

  • Continued drainage, street lighting, kerbing, fence installation and road surfacing between Wragby Road to Greetwell Road
  • Started weekend road closures at Greetwell Road for final roundabout works, including road markings, signage and street-lining.
  • Continue drainage works / begin street-lighting and kerbing works between Greetwell Road to Washingborough Road
  • Completed retention pond near new Washingborough Road roundabout
  • Began footway edging and surfacing between Washingborough and Lincoln Road (Branston)
  • Completed road markings, street-lining, kerbing and surfacing at Lincoln Road roundabout
  • Started final road surfacing between Lincoln Road (Branston) and Sleaford Road
  • Installed permanent parapets at Hawthorn Road footbridge
  • Completed concrete works for Greetwell footbridge
  • Completed wing wall stringcourses and deck waterproofing / installed verge ducts, deck kerb and drainage units for River Witham Viaduct
  • Completed finishing works / progresses approach paths for South Delph footbridge
  • Completed Hawthorn retaining wall
  • Installed kerbs, deck/drain units and carried out verge concrete works and deck water-proofing at Market Rasen Line rail bridge deck
  • Completed concrete finishing works at Bloxholm Lane footbridge

What's happening in October

  • Complete sign installation and street lighting change at Wragby Road
  • Complete drainage, street lighting and kerbing / continue fence installation and road surfacing between Wragby Road to Greetwell Road
  • Complete road markings, signage and street-lining on Greetwell Road roundabout
  • Continue drainage works, surfacing and kerbing works between Greetwell Road to Washingborough Road
  • Continue footway edging and surfacing /begin road surfacing, road markings and signage between Washingborough and Lincoln Road (Branston)
  • Complete final road surfacing, road markings and signage between Lincoln Road (Branston) and Sleaford Road
  • Continue final parapet works at Hawthorn Road footbridge
  • Install parapets and construct approach paths for Greetwell footbridge
  • Complete parapets, deck joints, concrete works and wing wall stringcourses for River Witham Viaduct
  • Complete approach paths for South Delph footbridge
  • Fit metal railings for Lincoln Road Underpass
  • Carry out works to north wing wall stringcourses / progress parapets for Market Rasen Line rail bridge deck
  • Install metal parapets and construct approach paths for Bloxholm Lane footbridge

Upcoming traffic restrictions and closures

  • Weekend road closures at Lincoln Road (Branston) from 6am Saturday morning until 6am Monday morning (road may be re-opened before 6am on Monday morning, dependant on how the works progress)
    • 3-5 October / 10-12 October
  • Weekend road closures at Greetwell Road from 6am Saturday morning until 6am Monday morning (road may be re-opened before 6am on Monday morning, dependant on how the works progress)
    • 3-5 October / 10-12 October / 17-19 October / 24-26 October

Current/ongoing traffic restrictions and closures

  • Full 24/7 closure of Washingborough Road and Hawthorn Road
  • Full 24/7 closure of Bloxholm Lane and Greetwell Fields Lane (new Bloxholm link off of Sleaford Road open)
  • Temporary speed restrictions on Heighington Road, Greetwell Road, Lincoln Road and Sleaford Road
  • Temporary 200m path diversion on the Sustrans route along the River Witham

*Please note this information is accurate as of the time of publication

Published: 2nd October 2020