Steel and concrete works to the first phase the A1 bridge are set to be completed in September.
What we achieved in August
- Continued steel and concrete works, waterproofing and backfill for A1 bridge
- Continued drainage works to the eastern and western roundabouts
- Continued ecological surveying for Phase Three
- Continued post-excavation archaeological reporting
What's happening in September
- Completion of steel and concrete works to the first phase the A1 bridge
- Carry out earthworks, pavement construction and surfacing to tie the new bridge into the A1
- Continue drainage works to the western side of the scheme
- Install temporary sheet piles on the A1
Upcoming traffic restrictions and closures
- Full night-time closure on the northbound A1 between Little Ponton and Harlaxton from from 8pm to 6am
- Tuesday 1 September to Friday 4 September
- Monday 7 September to Friday 11 September
- Wednesday 30 September
- Diversion route via A606 at Stamford to A607 to A1 at Harlaxton
Current/ongoing traffic restrictions and closures
-
50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton