Grantham Southern Relief Road update – Bridge beams installed to the west of the A1

GSRR beam lift

Sixteen 14+ tonne bridge beams were delivered and lifted into place in July.

What we achieved in July

  • Lifted bridge beams into place to the west of the A1 over three evenings
  • Continued bridge deck works
  • Continued drainage works to the eastern and western roundabouts
  • Carried out signage surveying works along the A1 verges
  • Carried out drainage tie-ins to the northbound and southbound A1
  • Completed archaeological works for Phase Three east of the railway
  • Progressed ecological surveying for Phase Three

What's happening in August

  • Continue steel and concrete works, waterproofing and backfill for A1 bridge
  • Continue drainage works to the eastern and western roundabouts
  • Continue ecological surveying for Phase Three

Upcoming traffic restrictions and closures

  • N/A

Current/ongoing traffic restrictions and closures

  • 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton

Published: 3rd August 2020