Drainage works and earthworks will be the main focus in June.
What we achieved in May
- Completed bored piling works to the western half of the new underpass
- Continued earthworks to the western and eastern roundabouts and slip roads, including lime modification
- Started drainage works for the eastern roundabouts
- Completed bored piling works and installed temporary sheet piling adjacent to the northbound A1
- Continued archaeological works for Phase Three east of the railway
- Carried out ground surveys and trial holes for Phase Three
What's happening in June
- Complete pile cropping and commence reinforced concrete works to underpass
- Complete current phase of earthworks and top soiling
- Continue drainage works to the eastern roundabout and commence drainage to the western roundabout
- Continue final archaeological works and carry out further geotechnical trial holes for Phase Three
Upcoming traffic restrictions and closures
- N/A
Current/ongoing traffic restrictions and closures
- 50mph speed limit and narrow lanes on the A1 between Harlaxton to Little Ponton