Fabrication and installation of bridge decks and parapets for the bypasses new footbridges will progress throughout June.
What we achieved in May
- Completed road lining on St Augustine’s Road
- Continued drainage and fencing between Wragby Road and Greetwell Road
- Installed WPD and street lighting ducts west of Washingborough Road
- Continued drainage and started kerbing at the new Washingborough Road roundabout
- Continued drainage and started footpath edging for non-motorised user area between Washingborough and Lincoln Road
- Begin installation of safety barriers & vehicle restraint systems and street lighting between Sleaford Road and Lincoln Road / began surfacing works for non-motorised user area between Bloxholm Lane and Lincoln Road
- Completed final carriageway surfacing and road markings for Sleaford Road roundabout
- Continued abutments and started fabrication of metal bridge deck for Greetwell footbridge
- Installed back of wall drainage and progressed backfill, concreting and fabrication of metal parapets for River Witham Viaduct
- Continued abutment works for South Delph footbridge
- Completed structural works for Lincoln Road underpass
- Excavated and constructed bases for Hawthorn retaining wall
- Continued abutment/wing wall works and fabricated metal deck for Bloxholm Lane footbridge
- Continued post-excavation archaeological reporting
What's happening in June
- Continue drainage and fencing, and begin kerbing and ducting installation between Wragby Road to Greetwell Road
- Begin pond drainage between Greetwell Road to Washingborough Road
- Continue drainage, kerbing and installation of WPD and street lighting ducts at Washingborough Road roundabout
- Continue drainage and footpath edging for non-motorised user area / commence kerbing between Washingborough and Lincoln Road
- Continue raising gullies and fencing works between Lincoln Road and Sleaford Road
- Begin top soiling and preparing for seeding between Sleaford Road and Lincoln Road
- Fabricate permanent parapets for Hawthorn Road footbridge
- Continue abutments for Greetwell footbridge
- Complete backfill and concrete string courses for River Witham Viaduct
- Carry out finishing works for South Delph footbridge
- Construct wall structure for Hawthorn retaining wall
- Complete abutment/wing wall works and commence concrete string courses for Bloxholm Lane footbridge
- Continue post-excavation archaeological reporting
Upcoming traffic restrictions and closures
-
N/A
Current/ongoing traffic restrictions and closures
- Full 24/7 closure of Washingborough Road and Hawthorn Road
- Full 24/7 closure of Bloxholm Lane and Greetwell Fields Lane
- Temporary speed restrictions on Heighington Road, Greetwell Road, Lincoln Road and Sleaford Road
- Temporary 200m path diversion on the Sustrans route along the River Witham
- Temporary two-way traffic signals at B1188 Lincoln Road roundabout and A15 Sleaford Road roundabout (when needed)
*Please note this information is accurate as of the time of publication