The closure will allow Galliford Try to carry out piling works for the new bridged junction.
What we achieved in March
- Progressed piling works to the western half of the new bridge's underpass
- Recommenced earthworks to the western and eastern roundabout and slip roads, including lime modification
- Completed Anglian Water diversion
- Completed site clearance and continued archaeological works for Phase Three
What's happening in April
- Continue piling works to the western half of the new bridge's underpass
- Continue earthworks to the western and eastern roundabout and slip roads, including lime modification
- Carry out piling works adjacent to the A1's northbound carriageway
- Continue final archaeological works for Phase Three
Upcoming traffic restrictions and closures
- Full night-time lane closure on the northbound A1 between Little Ponton and Harlaxton from Sunday 26 April to Friday 1 May from 8pm to 6am
- Diversion route via A606 at Stamford to A607 to A1 at Harlaxton
Current/ongoing traffic restrictions and closures
- 50mph speed limit and narrow lanes on the A1 between Harlaxton to Little Ponton