Works to build Lincoln's new bypass are continuing forward.
What we achieved in March
- Installed new kerbs, footpaths and surfacing at St Augustine Road / Hawthorn Road junction
- Continued earthworks and drainage installation for new Washingborough Road roundabout
- Continued filter drain installation between Sleaford Road and Lincoln Road
- Completed street lighting and final drainage works at Sleaford Road roundabout
- Completed and backfilled construct bases for Greetwell footbridge, and progressed east wall
- Continued deck and wing wall works for River Witham Viaduct
- Carried out deck works for South Delph footbridge
- Completed structural works for Lincoln Road underpass
- Continued abutment and wing wall works for Bloxholm Lane footbridge
- Continued post-excavation archaeological reporting
What's happening in April
- Begin drainage installation between Wragby Road and Greetwell Road
- Continue earthworks and drainage installation for new Washingborough Road roundabout
- Continue filter drain installation and raising gullies between Sleaford Road and Lincoln Road
- Commence drainage works between Washingborough Road and Heighington Road
- Carry out final kerbing works at Sleaford Road roundabout
- Fabricate permanent parapets for Hawthorn Road footbridge
- Complete east abutment; progress east wing walls and west abutment; and fabricate metal bridge deck for Greetwell footbridge
- Complete decking concrete pours and continued wing wall, parapet and rebar works for River Witham Viaduct
- Continue abutment works for South Delph footbridge
- Continue abutment and wing wall works and fabricate metal bridge deck for Bloxholm Lane footbridge
- Continue post-excavation archaeological reporting
Upcoming traffic restrictions and closures
- Weekend road closures on Sleaford Road from:
- 7pm on Friday 24 April to 6am on Monday 27 April
- 7pm on Friday 1 May to 6am on Monday 4 May
- 7pm on Friday 15 May to 6am on Monday 18 May
Current/ongoing traffic restrictions and closures
- Full 24/7 closure of Washingborough Road and Hawthorn Road
- Full 24/7 closure of Bloxholm Lane and Greetwell Fields Lane
- Temporary speed restrictions on Heighington Road, Greetwell Road, Lincoln Road and Sleaford Road
- Temporary 200m path diversion on the Sustrans route along the River Witham
- Temporary two-way traffic signals at B1188 Lincoln Road roundabout until Thursday 7 May
*Please note this information is accurate as of the time of publication