Coastal Carriageway March 2025 update

Broadway 1

An overview of progress on the Coastal Carriageway improvement project.

What we achieved in February

Old Roman Bank

  • Completed reconstruction of the road between Anderby and Chapel St. Leonards
  • Reconstructed the Sea Lane / Huttoft Junction
  • Reconstructed the junction to Anderby Creek
  • Installed new drainage and kerbing in Chapel St. Leonards

Broadway / York Road in Sutton on Sea

  • Completed Phase 1 of the works including footway and carriageway surfacing
  • Installed all drainage on Phase 2 (Marisco Court to Broadway surgery)
  • Removed the existing concrete road construction on Phase 2
  • Installed new kerbs for Phase 2

What’s happening in March

Old Roman Bank

  • Finish road reconstruction in Chapel St. Leonards
  • Complete all remaining road markings throughout the project extents
  • Complete the reconstruction of verges and install new passing bay signage

Broadway / York Road in Sutton on Sea

  • Commence works on Phase 3 (Surgery to York Road)
  • Construct new access to Broadway car park
  • Complete surfacing to footway and carriageway on Phase 2
  • Install drainage catchpits on York Road/Broadway junction

Current/ongoing traffic restrictions and closures

Old Roman Bank

  • Ongoing road closure between Sandilands and Anderby Creek & Anderby Creek and Chapel St Leonards

Broadway / York Road in Sutton on Sea

  • Road and footway closure on Broadway, between Marisco Court and surgery until mid-March

Upcoming traffic restrictions and closures

Old Roman Bank

  • Night-time road closures as required in February/March outside the observatory up to the junction with Ancaster Avenue

Broadway / York Road in Sutton on Sea

  • Road and footway closure on Broadway, between surgery and York Road from mid-March

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/coastalcarriageway.

Funded by Uk Gov Logo

Published: 3rd March 2025