An overview of progress on the Grantham Southern Relief Road project
What we achieved in December
- East side of site – lift Span 7 bridge beams into position / install all bracing member to Span 7
What's happening in January
- East side of site – lift Span 7 bridge beams into position / install all bracing member to Span 7 / grout bearings into position for span 7 / remove temporary works from beneath the bridge beams / begin formwork, reinforcement and concrete works to complete the ballast walls and wingwalls
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A