A16 Pinchbeck Roundabout January update

Pinchbeck Rbout Jan 2025

An overview of progress on the Pinchbeck Roundabout improvement project

What we achieved in December

  • Surface the widened carriageway on the southwest side
  • Surface the eastern leg of the roundabout
  • Topsoil dressing along the southwest and northwest verges
  • Installed, wired and powered on street lighting columns on the southwest and northwest sides
  •  Completed building the south island and both B1180 islands
  • Started the west half of the north splitter island

What’s happening in January

  • Complete building the splitter islands
  • Prepare for final surfacing
  • Complete sections of outstanding earthworks
  • Begin site clearance
  • Start laying final road surfacing / implement night-time road closures of A16

Current/ongoing traffic restrictions and closures

  • Ongoing narrowed lanes on A16 in the roundabout and all its approaches
  • Narrowed lanes in the roundabout and all its approaches

Upcoming traffic restrictions 

  • TBC

Published: 2nd January 2025