A16 Pinchbeck Roundabout January update

Pinchbeck Rbout Jan 2025

An overview of progress on the Pinchbeck Roundabout improvement project

What we achieved in December

  • Surface the widened carriageway on the southwest side
  • Surface the eastern leg of the roundabout
  • Topsoil dressing along the southwest and northwest verges
  • Installed, wired and powered on street lighting columns on the southwest and northwest sides
  •  Completed building the south island and both B1180 islands
  • Started the west half of the north splitter island

What’s happening in January

  • Complete building the splitter islands
  • Prepare for final surfacing
  • Complete sections of outstanding earthworks
  • Begin site clearance
  • Start laying final road surfacing / implement night-time road closures of A16

Current/ongoing traffic restrictions and closures

  • Ongoing narrowed lanes on A16 in the roundabout and all its approaches
  • Narrowed lanes in the roundabout and all its approaches

Upcoming traffic restrictions 

  • Night-time road closures on the A16 starting on Monday 20 January for up to two months, 8pm to 6am, between Ten Acre Lane and Springfield Roundabout
    • A16 North diversion route – via A151 / A17, and vice versa 
    • A16 South diversion route – via A16 / A152 / B1356, and vice versa

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/pinchbeckroundabout.

Funded by Uk Gov Logo

Published: 2nd January 2025