Coastal Carriageway January update

Coastal Carriageway Jan 2025

An overview of progress on the Coastal Carriageway improvement project

What we achieved in December

Old Roman Bank

  • Completed new surfacing from the A52 in Sandilands through to Sea Lane
  • Completed the reinstatement of ironworks in Sandilands
  • Completed the new lining in Sandilands
  • Mostly complete verge reconstruction between Sandilands and Sea Lane
  • Competed the reconstruction of carriageway between Sea Lane and Anderby Creek
  • Started excavation for passing bays between Anderby Creek and Chapel St. Leonards

A1104 Maltby le Marsh / Mablethorpe 

  • Completed earthworks to lower verge along Main Road and Alford Road in Mablethorpe
  • Completed excavation works and carriageway reconstruction works along Main Road and Alford Road, including the junctions of Mile Lane and A1031
  • Installed new road markings

What’s happening in January

Old Roman Bank

  • Re-constructing the verges between Sea Lane and Anderby Creek
  • Reconstruction of the carriageway between Anderby Creek and Chapel St.Leonards
  • Night time works required to complete the Sea Lane and Old Roman Bank junction
  • Excavation of passing bays between Anderby Creek and Chapel St.Leonards

Broadway / York Road in Sutton on Sea

  • Establish site compound 
  • Install new carrier drain and commence new manhole construction on Broadway
  • Commence footpath works between Station Road and Marisco Court
  • Excavate existing concrete carriageway and trim to formation
  • Lay base and binder course layers between Station Road and Marisco Court

Current/ongoing traffic restrictions and closures

Old Roman Bank

  • Ongoing road closure between Sandilands and Anderby Creek & Anderby Creek and Chapel St Leonards

Upcoming traffic restrictions and closures

Old Roman Bank

  • Night-time road closures required to complete the Sea Lane and Old Roman Bank junction in mid-January

Broadway / York Road in Sutton on Sea

  • 24/7 road closure on Broadway from A52 Station Road to Marisco Court starting on Monday 6 January

Published: 2nd January 2025