Sincil Bank improvements January update

Sincil bank

An overview of progress on the Sincil Bank improvement project

What we achieved in December

  • Replaced damaged kerbs and resurfaced footway on both sides from Ripon Street to Kirkby Street 
  • Excavated and installed two new build-out areas and pedestrian crossing areas near Ripon Street and Kirkby Street
  • Installed new gully pots along the route from Ripon Street to Kirkby Street
  • Carried out repairs to the existing drainage system

What’s happening in January

  • Replace damaged kerbs and resurface the footways on both sides from Kirkby Street to Scorer Street 
  • Re-lay some of the existing channel blocks
  • Improve existing crossing point at Hood Street
  • Carry out carriageway resurfacing works

Current/ongoing traffic restrictions and closures

  • 24/7 closure from Kirkby Street to Scorer Street
  • Diversion route is via Cross Street and Ripon Street 
  • Road closure for resurfacing works at Kesteven Street

Upcoming traffic restrictions and closures

  • Parking restrictions from Kirkby Street to Scorer Street
  • Parking restrictions on Kesteven Street

Published: 2nd January 2025