What we achieved in November

  • Installed new kerbs and resurfaced footway on both sides from Portland Street to Ripon Street
  • Excavated and installed two new build-out areas and pedestrian crossing areas near Chelmsford Street and Ripon Street
  • Installed new gully pots along the route from Kesteven Street to Ripon Street
  • Carried out repairs to the existing drainage system

What’s happening in December

  • Install new kerbs and footways from Ripon Street to Kirby Street
  • Install two new build-out and pedestrian crossing areas between Ripon Street and Kirkby Street
  • Carry out additional drainage works

Current/ongoing traffic restrictions and closures

  • 24/7 barriers and one-way system on Sincil Bank, from Ripon Street to Kirby Street
    • Diversion route is via Cross Street
    • This section may be temporarily closed depending on the activities taking place on site

Upcoming traffic restrictions and closures

  • Parking restrictions from Ripon Street to Kirkby Street

For more information about this project visit www.lincolnshire.gov.uk/sincilbankimprovements.