A16 Pinchbeck Roundabout December update

Pinchbeck Roundabout December update

What we achieved in November

  • Drainage works along the northwest and southwest sides of the A16
  • Drainage works and earthworks on the eastern leg of the roundabout
  • Carriageway widening and installation of the new keyline on the southwest side of the A16
  • Installed new kerb line along the northwest side of the A16
  • Started construction of the dedicated left-turn splitter island into the B1180
  • Installed the new traffic signs on the western side of the A16

What’s happening in December

  • Surface the widened carriageway on the southwest side of the A16 and the eastern leg of the roundabout
  • Install the rest of the street lighting columns, cabling and switch them on
  • Install traffic management for narrowed lanes at the location of new splitter islands
  • Complete construction of the new splitter islands

Current/ongoing traffic restrictions and closures

  • Ongoing narrowed lanes on A16 in the roundabout and all its approaches
  • Narrowed lanes in the roundabout and all its approaches.

Upcoming traffic restrictions

  • N/A

For more information about this project visit www.lincolnshire.gov.uk/pinchbeckroundabout.

Funded by Uk Gov Logo

Published: 2nd December 2024