What we achieved in November
- Completed footway works on the northside of site, from Coles Way to Barrowby Gate
- Started kerbing at the eastern end of Dysart Road, from Trent Road to Low Road
- Continued night-time resurfacing and road reconstruction work on the carriageway, starting at the railway bridge and heading west along Dysart Road
- Continued drainage repairs, channel repairs and kerbing works
What’s happening in December
- Finish the footway works on the northside of site, from Yarmouth Avenue to Barrowby Gate
- Complete footway surfacing works continuing along Dysart Road
- Carry out footway works west of Trent Road on Dysart Road
- Carry out final drainage repairs, channel repairs and kerbing works
Current/ongoing traffic restrictions and closures
- 24/7 westbound closure of Dysart Road
- Temporary traffic signals west of Trent Road, on Dysart Road
- Night-time closures for carriageway reconstruction works (between Dysart Road railway bridge and Trent Road) until early December, weekday evenings only, 7pm to 6am
Upcoming traffic restrictions and closures
- Daytime closures for carriageway reconstruction works (from Trent Road to Low Road – just west of the A1 overbridge) starting Monday 9 December for two weeks, weekdays only, 6am to 6pm
- The westbound closure on Dysart Road is being removed and the road reverting back to a two-way flow from Saturday 7 December
For more information about this project visit www.lincolnshire.gov.uk/dysartroad.