Sincil Bank improvements November update

Sincil Bank November update

The latest update on the Sincil Bank improvements.

What we achieved in October

  • Installed new kerbs and footway from Kesteven Street to Portland Street
  • Laid footway resurfacing from Portland street to Chelmsford street
  • Excavation and installation of two new build-out areas and pedestrian crossing areas from Portland Street to Chelmsford Street

What’s happening in November

  • Install new kerbs and footways from Chelmsford Street to Ripon Street
  • Install two new build-out and pedestrian crossing areas between Chelmsford Street and Ripon Street

Current/ongoing traffic restrictions and closures

  • 24/7 barriers and one-way system on Sincil Bank, from Portland Street to Chelmsford street
    • Diversion route is via Trollope Street

Upcoming traffic restrictions and closures

  • Parking restrictions on Chelmsford Street to Ripon Street starting w/c 4th November
  • One-way on Sincil Bank between Chelmsford Street and Ripon Street
    • Diversion route via Cross Street

For more information about this project visit www.lincolnshire.gov.uk/sincilbankimprovements.

Published: 4th November 2024