Grantham Southern Relief Road November update

Grantham Southern Relief Road November update

The latest update on the Grantham Southern Relief Road.

What we achieved in October

Phase Three
  • East side of site – completed sub-base to eastern embankment / concreting to in line wingwalls / fixed reinforcement, concrete and shuttering to ballast wall

What's happening in November

Phase Three
  • East side of site – strip ballast wall shutters / delivery of Span 7 bridge beams / slice beams together / install temporary works to eastern abutment and Pier 6 for beam lift

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

For more information about this project visit www.lincolnshire.gov.uk/gsrr.

Published: 4th November 2024