A16 Pinchbeck Roundabout November update

Pinchbeck Roundabout November update.

The latest update on the A16 Pinchbeck Roundabout Improvements.

What we achieved in October

  • Built the new circular island, including the new signs
  • Surfaced the void of the existing island and switched traffic management
  • Installed street lighting ducts
  • Started site clearance and drainage work along the northwest and southwest sides of A16

What’s happening in November

  • Continue drainage work on the northwest and southwest sides of A16
  • Carriageway widening and installation of the new keyline on the southwest side of the A16
  • Install new kerb line along the northwest side of the A16
  • Complete earthwork along the east leg of the roundabout

Current/ongoing traffic restrictions and closures

  • Ongoing narrowed lanes on A16 in the roundabout and all its approaches

Upcoming traffic restrictions

  • N/A

For more information about this project visit www.lincolnshire.gov.uk/pinchbeckroundabout.

Funded by Uk Gov Logo

Published: 4th November 2024