The latest update on the A16 Pinchbeck Roundabout Improvements.
What we achieved in October
- Built the new circular island, including the new signs
- Surfaced the void of the existing island and switched traffic management
- Installed street lighting ducts
- Started site clearance and drainage work along the northwest and southwest sides of A16
What’s happening in November
- Continue drainage work on the northwest and southwest sides of A16
- Carriageway widening and installation of the new keyline on the southwest side of the A16
- Install new kerb line along the northwest side of the A16
- Complete earthwork along the east leg of the roundabout
Current/ongoing traffic restrictions and closures
- Ongoing narrowed lanes on A16 in the roundabout and all its approaches
Upcoming traffic restrictions
- N/A
For more information about this project visit www.lincolnshire.gov.uk/pinchbeckroundabout.