What we achieved in September

  • Set-up site compound
  • Excavated existing footway and kerbs / built new footway / installed new kerbs along the dike side from Kesteven Street to Portland Street
  • Renewed tactile paving for crossing
  • Excavated existing footway and kerbs and started install of new kerbs for the new footway on the residential side from Kesteven Street to Portland Street

What’s happening in October

  • Finish new kerbs for new footway on residential side from Kesteven Street to Portland Street
  • Prepare footway foundation for the new surface
  • Continue excavating existing footway around southern side of Kesteven Street

Current/ongoing traffic restrictions and closures

  • 24/7 barriers and temporary lights on Portland Street/Kesteven Street/Sincil Bank

Upcoming traffic restrictions and closures

  • 24/7 barriers and narrowing of Kesteven Street to complete the footway works at the south and north footways

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.

Published: 2nd October 2024