A16 Springfield Roundabout October update

A16 Springfield Roundabout October

The latest update on the A16 Springfield Roundabout.

What we achieved in September

  • Start and finish new kerbs in the roundabout centre
  • Seeding of topsoiled verges will continued across the site
  • Started installation of boundary fencing
  • Completed half of the final road surfacing for the roundabout
  • Completed 90% of footpath surfacing
  • Continued installing scheme signs site-wide
  • Switched on lighting columns on A151 East

What’s happening in October

  • Complete final surfacing and road markings
  • Install safety barrier in the roundabout centre
  • Finish topsoil, seeding and installation of fencing

Current/ongoing traffic restrictions and closures

  • 24/7 barriers at the roundabout, with the current single-lane entries and single-lane exits
  • Ongoing narrowed roundabout lanes during the day
  • Ongoing night time closures and traffic signals

Upcoming traffic restrictions and closures

Night-time temporary traffic lights (dates TBC)

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.

Published: 2nd October 2024