The latest update on the Grantham Southern Relief Road.
What we achieved in September
Phase Three
- East side of site – completed crane platform and access track behind east abutment / fixed reinforcement and shuttering to east abutment in line wingwalls / started road-box dig and sub-base to eastern embankment
What's happening in October
Phase Three
- East side of site – complete Sub-base to eastern embankment / fixed reinforcement and shuttering to ballast wall / concreting to in line wingwalls
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A
For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.