Grantham Southern Relief Road October update

Grantham Southern Relief Road October 2024 update

The latest update on the Grantham Southern Relief Road.

What we achieved in September

Phase Three

  • East side of site – completed crane platform and access track behind east abutment / fixed reinforcement and shuttering to east abutment in line wingwalls / started road-box dig and sub-base to eastern embankment

What's happening in October

Phase Three

  • East side of site – complete Sub-base to eastern embankment / fixed reinforcement and shuttering to ballast wall / concreting to in line wingwalls

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.

Published: 2nd October 2024