A16 Pinchbeck Roundabout October update

A16 Pinchbeck Roundabout October update

The latest update on the A16 Pinchbeck Roundabout.

What we achieved in September

  • Re-opened B1180 to traffic
  • Surfaced the widened sections of A16 North and South
  • Installed street lighting columns on the eastern side of the A16
  • Cleared existing circular island and started construction of new circular island
  • Topsoiled the remaining verges along A16 embankment
  • Filled the embankment for the leg going the northeast of the roundabout

What’s happening in October

  • Surface the footprint of existing circular island
  • Carry out drainage works within new island
  • Install traffic ducting in the new island and on A16
  • Start works on northwest and southwest A16

Current/ongoing traffic restrictions and closures

  • Ongoing narrowed lanes on A16 in the roundabout and all its approaches

Upcoming traffic restrictions

  • N/A

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.

Funded by Uk Gov Logo

Published: 2nd October 2024