What we achieved in September
- Re-opened B1180 to traffic
- Surfaced the widened sections of A16 North and South
- Installed street lighting columns on the eastern side of the A16
- Cleared existing circular island and started construction of new circular island
- Topsoiled the remaining verges along A16 embankment
- Filled the embankment for the leg going the northeast of the roundabout
What’s happening in October
- Surface the footprint of existing circular island
- Carry out drainage works within new island
- Install traffic ducting in the new island and on A16
- Start works on northwest and southwest A16
Current/ongoing traffic restrictions and closures
- Ongoing narrowed lanes on A16 in the roundabout and all its approaches
Upcoming traffic restrictions
- N/A