The latest update on the Coastal Carriageway Improvements.
What we achieved in September
Old Roman Bank
- Mobilisation to site, site compound set up
- Works commenced 16th September at Sandilands end of scheme moving southwards
- Removal of 1.5km length of existing carriageway and commencement of new carriageway surfacing
- Removal of existing footway and commencement of new surfacing
A1104 Maltby le Marsh / Mablethorpe
- Contractor appointed for carriageway reconstruction, minor footway works and earthworks to lower the verge
What’s happening in October
Old Roman Bank
- Continuation of the works between Sandilands and Anderby Creek, carriageway and footway
- Commencement of the 2nd section of works south of Anderby Creek to Chapel St Leonards, 8th October
A1104 Maltby le Marsh / Mablethorpe
- Set-up site compound / contractor mobilisation
- Install traffic management
- Begin footway reconstruction and excavation of carriageway
- Begin earthworks to lower the verge along Alford Road and Main Road in Maltby Le Marsh
Current/ongoing traffic restrictions and closures
Old Roman Bank
- Temporary Traffic Signals at A52 end of Sandilands
- Ongoing road closure between Sandilands and Anderby Creek
A1104 Maltby le Marsh / Mablethorpe
- N/A
Upcoming traffic restrictions and closures
Old Roman Bank
- Additional road closure of section between Anderby Creek and Chapel St Leonards
A1104 Maltby le Marsh / Mablethorpe
- A combination of daytime and night-time road closures will be in place throughout the works:
- Thursday 17 October to late November – night-time road closure from 7pm to 7am
- Monday 2 December to mid-December – daytime closure from 8:30am to 6:30pm
- Temporary traffic signals will also be in use as needed during the project.
For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.