The latest update on the Grantham Southern Relief Road.
What we achieved in August
Phase Three
- East side of site – backfill to east abutment / construct crane platform behind east abutment
What's happening in September
Phase Three
- East side of site – complete crane platform and access track behind east abutment / reinforcement and shuttering to east abutment ballast wall / concrete east abutment ballast wall
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A