The latest update on Grantham Market Place.
What we achieved in July
- Kerbs and concrete base slabs removed from the Conduit Lane carriageway entrance raised table
- Kerbs re-laid at new levels at Conduit Lane raised table
- Removed existing brick arched cover to well and replaced with a pre-cast concrete cover slab
- Asphalt foundation to Market Place
- Laid new granite cobbles and Yorkstone setts to 420 square metres of Westgate Road, Conduit Lane and the laybys
What’s happening in August
- Continue laying granite cobbles and Yorkstone setts, including applying jointing material
Current/ongoing traffic restrictions and closures
- Full road closure of the Market Place and a soft closure on Conduit Lane (access maintained for taxi rank)
- 24/7 barriers around the whole Market Place construction area (all pedestrian areas are accessible)
- Access maintained to the footway outside the Conduit Lane Tearooms and the Reflect Recruitment Offices
- Removed bollards at the top of Butchers Walk for ease of deliveries to businesses
- Loading areas maintained at the top of Market Place junction with Watergate and on Narrow Westgate
Upcoming traffic restrictions and closures
- No changes expected