A16 Pinchbeck Roundabout August update

An overhead view of the Pinchbeck roundabout

The latest update on Pinchbeck Roundabout.

What we achieved in July

  • Closed B1180 and installed traffic management
  • Completed reinforced earth embankment on the northside of B1180
  • Completed outfall manhole and road crossing drainage run on B1180
  • Cleared the existing kerb line along the north and south sides of B1180
  • Diverted Vodafone duct along the north verge of B1180
  • Diverted Openreach duct on the south and north sides of B1180
  • Completed earthworks on the northeast and southeast sides of A16
  • Started drainage works on the northeast side of A16
  • Started construction widened sections of road along northeast side of A16 and north side of B1180

What’s happening in August

  • Complete drainage works along A16 North, A16 South, and B1180 (as far as the closure allows for safe working)
  • Construct the widened sections of the carriageway along A16 and B1180
  • Lay surfacing to the widened sections along A16 and B1180

Current/ongoing traffic restrictions and closures

  • 24/7 closure of B1180 until mid-September
  • Ongoing narrowed lanes along the South and the North approaches of the roundabout.

Upcoming traffic restrictions

  • Night-time temporary traffic signals on the A16 (as needed) to install road crossing ducts for new street lighting

Published: 2nd August 2024