The latest update on the Grantham Southern Relief Road.
What we achieved in July
Phase Three
- East side of site – concreting to south wingwall at east abutment; concreting to Pier 6 plinths / reinforcement, shuttering and concrete to north wingwall / B.O.W. drainage to wing walls
What's happening in August
Phase Three
- East side of site – backfill to east abutment / construct crane platform behind east abutment
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A