A16 Springfield Roundabout August update

Springfield Roundabout overhead view

The latest update on the A16 Springfield Roundabout.

What we achieved in July

  • Removed all the old kerbs and footpath / laid all new kerbs in the northwest corner
  • Completed earthworks and drainage in the northwest corner
  • Completed new culvert works in the northeast corner outside McDonalds
  • Installed new lighting columns and sign post foundations throughout site
  • Switched traffic management to allow access to the roundabout centre and northeast corner outside McDonalds
  • Removed block paving and vegetation in the roundabout centre

What’s happening in August

  • New drainage to be installed in the northeast corner and roundabout centre
  • Start and finish new kerbs in the roundabout centre
  • Finish footpaths in the northwest corner
  • Complete low voltage diversion, BT diversion and start laying new kerbs in the northeast corner

Current/ongoing traffic restrictions and closures

  • 24/7 barriers at the roundabout, with the current single-lane entries and single-lane exits
  • Ongoing narrowed roundabout lanes

Upcoming traffic restrictions and closures

  • Night-time closures for final surfacing in October

Published: 2nd August 2024