What we achieved in June

Phase Three

  • East side of site – fix reinforcement and shuttering to south wingwall at east abutment / concreting works to Pier 6 / completed scaffold removal for Pier 5

What's happening in July

Phase Three

  • East side of site – concreting to south wingwall at east abutment; concreting to Pier 6 plinths / reinforcement, shuttering and concrete to north wingwall

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd July 2024