The latest update on Pinchbeck Roundabout.
What we achieved in June
- Finished clearance works along A16 North, A16 South and southwest side of B1180
- Began earthworks on A16 North and A16 South
- Began earthworks on southwest side of B1180
What’s happening in July
- Continue of earthworks on A16 North, A16 South and southwest side of B1180
- Carry out drainage work on southwest side of B1180
- Carry out Vodafone and Openreach utility works on-site
Current/ongoing traffic restrictions and closures
- 24/7 barriers at the roundabout, along northbound A16 and eastbound B1180
- Ongoing narrowed roundabout lanes
Upcoming traffic restrictions and closures
- Full closure of B1180 leg of roundabout starting on Monday 15 July for up to eight weeks
- Diversion route via Wardentree Lane / B1180 / B1356 / A152 / A16, and vice versa