The latest update on the A16 Springfield Roundabout.
What we achieved in June
- Continued earthworks and drainage in the northwest corner
- Removed all the old kerbs and footpath in the northwest corner
- Completed some of the final surfacing to the A16 North and A16 South
- Started new culvert works in the northeast corner outside McDonalds
What’s happening in July
- Installation of new lighting columns across the whole job
- Installation of new signage across the whole job
- Finish drainage and earthworks in the northwest corner
- Start and finish new kerbs in the northwest corner
- Start and finish new footpaths in the northwest corner
Current/ongoing traffic restrictions and closures
- 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits
- Ongoing narrowed roundabout lanes
Upcoming traffic restrictions and closures
- Night-time temporary traffic lights from 8th to 12th July, 8pm to 6am