Grantham Southern Relief Road June 2024 update

A view of the latest work on the Grantham Southern Relief Road

The latest update on the Grantham Southern Relief Road.

What we achieved in May

Phase Three

  • West side of site – completed installation of Pier 3 stabilising working platforms
  • East side of site – fixed reinforcement, shuttering and concrete to east abutment wingwalls / fixed reinforcement and shuttering to Pier 6 main wall / stripped Soffit shuttering from Pier 5

What's happening in June

Phase Three

  • East side of site – fix reinforcement, shuttering and concrete to south wingwall at east abutment / concreting to Pier 6 / complete scaffold removal for Pier 5

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 4th June 2024