The latest update on the Grantham Southern Relief Road.
What we achieved in May
Phase Three
- West side of site – completed installation of Pier 3 stabilising working platforms
- East side of site – fixed reinforcement, shuttering and concrete to east abutment wingwalls / fixed reinforcement and shuttering to Pier 6 main wall / stripped Soffit shuttering from Pier 5
What's happening in June
Phase Three
- East side of site – fix reinforcement, shuttering and concrete to south wingwall at east abutment / concreting to Pier 6 / complete scaffold removal for Pier 5
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A