The latest update on the A16 Springfield Roundabout.
What we achieved in May
- Finished earthworks and drainage in the southeast corner
- Completed footpaths on the south side of the roundabout
- Switched to new working areas in the northeast on the A151 and northwest corners
- Started earthworks and drainage works in the northeast corner, including the addition of a new section of culvert
- Continued earthworks and drainage in the northwest corner
- Start laying new road surfacing
What’s happening in June
- Continue laying new road surfacing
- Carry out culvert construction
- Continue drainage and earthworks in the northwest corner
Current/ongoing traffic restrictions and closures
- 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits
- Ongoing narrowed roundabout lanes
- Night time closures on the A16 for the first week of June
Upcoming traffic restrictions and closures
- 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits