Major improvements set for A151 in and near Bourne

Resurfacing

Works to rebuild sections of the A151 near Bourne will start next month.

Cllr Richard Davies, executive member for highways, said: “There are three sections of the A151, in Edenham, Bourne and Guthram Gowt, that are nearing the end of their serviceable life, so we’ve taken the decision to be rebuild them before they get any worse. 

“As part of these works, we’ll be using over 5,700 tonnes of tarmac and other road-building materials to carry this important project out.

“While on site, we’ll also be taking the opportunity to carry out some other maintenance including gully and manhole replacements and a refurb of the traffic signals at the bridge south of Edenham.”

Dates and timeframes

Monday 13th May for up to ten weeks

Location of works

  • 13th May – Edenham, between Copy Lawn Farm and Ancaster Court
  • 3rd June – Bourne, between Spalding road’s junction with Eastgate and just east of Meadow Drove
  • 2nd July – Guthram Gowt, between Guthram Gowt and Six House Bank

Traffic management

Night-time road closures from 7pm to 6am (weekdays only)

Diversion route

Edenham: A151 / A15 / A52 / B1176, and vice versa

Bourne and Guthram Gowt: Spalding Road / Eastgate/Willoughby Road / Cherry Holt Road / A15 / A1175 / A16, and vice versa

Cllr Davies added: “We'll be doing everything we can during the works to keep disruption to a minimum, including maintaining access for residents and emergency vehicles during our working hours.”

For up-to-date information about this and other roadworks, please visit www.lincolnshire.gov.uk/roadworks.

Published: 9th May 2024