The latest update on the Grantham Southern Relief Road.
What we achieved in April
Phase Three
- West side of site – started installing Pier 3 stabilising working platforms
- East side of site – concrete main abutment wall / cast masking walls and bearing plinths to Pier 5 / add reinforcement and formwork to east abutment wall / complete backfilling to Pier 6 base
What's happening in May
Phase Three
- West side of site – complete install of Pier 3 stabilising working platforms
- East side of site – fix reinforcement and shuttering to wingwall 1 / first concrete pour for wingwall 1 / partially strip scaffolding from Pier 5
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A