The latest update on the Spalding Western Relief Road.
What we achieved in January/February/March
- Completed settlement of and continued surcharge removal at the west junction and low height embankment
- Completed remaining bridge deck pours
- Completed construction of retaining wall
- Completed construction of the bridge deck
- Finished landscaping installation works in 5A
- Completed speed edging on east and west embankment
- Started constructing and pouring parapet ground beams
What's happening in April/May/June
- Install kerbing, drainage and street lighting at western junction
- Install pre-cast parapet units on top of the wall up to the bridge
- Carry out roundabout remedials works
- Tarmac installation of carriageway starting from ch1100
- Begin Two Plank footbridge pre-construction and construction stages
- Work on footpath/cycleways and maintenance track on the west side of the site
- Continue constructing and pouring parapet ground beams
Current/ongoing traffic restrictions and closures
- Closure of Two Plank Bridge and Blue Gowt Lane
- Closure of public right of way 15/1 and Two Plank Lane for bridge footpath construction until Summer 2024
Upcoming traffic restrictions and closures
- Night-time closures of Spalding Road roundabout – dates and details to be confirmed