The latest update on the Grantham Southern Relief Road.
What we achieved in March
Phase Three
- West side of site – concreted corbels on western bankseat / installed bridge launch equipment
- East side of site – completed backfill to east abutment base / began formwork to east abutment / shuttered and concreted Pier 5 crosshead / concreted and started backfilling Pier 6 base
What's happening in April
Phase Three
- West side of site – install Pier 3 stabilising working platforms
- East side of site – continue formwork and reinforcement to east abutment wall / cast masking walls and bearing plinths to Pier 5 / add reinforcement and formwork to Pier 6 wall / complete backfilling to Pier 6 base
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A