The latest update on the A16 Springfield roundabout.
What we achieved in March
- Finished earthworks; kerbing and drainage; and constructing new carriageway in the northeast and southwest corners
- Installed street light ducting
- Continued building the new footways and topsoiling verges
- Switched to new working areas in the northwest and southeast
- Started earthworks and drainage works in the northwest and southeast corners
- Started BT diversion in the southeast corner
What’s happening in April
- Switching to new working areas in the northwest and southeast
- Continue earthworks and drainage works in the northwest and southeast
- Continue BT diversion in the southeast corner
- Construct new carriageway in the northwest corner
- Start laying new kerbs
Current/ongoing traffic restrictions and closures
- 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits
- Ongoing narrowed roundabout lanes
Upcoming traffic restrictions and closures
- N/A