The latest update on the Grantham Southern Relief Road.
What we achieved in February
Phase Three
-
West side of site – reinforced fixing on bridge deck / installed of cantilever formwork / concreted bearing plinths
- East side of site – concreted east abutment main base / reinforcement and shuttering to north wingwall base / concreted north wingwall base / started backfilling east abutment base / reinforcement and temporary decking to Pier 5 / shuttering and reinforcement to Pier 6 base
What's happening in March
Phase Three
- West side of site – concrete corbels on western bankseat / install bridge launch equipment
- East side of site – complete backfill to east abutment base / begin formwork to east abutment / shuttering and concreting Pier 5 crosshead / concrete and begin backfilling to Pier 6 base
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A